If a vacant commercial property inspection cannot be completed, record it as partial or missed, tell the person responsible for the building what remains unchecked, and agree who will arrange a safe return visit. A perimeter check can still provide useful evidence. The report should show exactly which checks it covered and which are still outstanding.
Stop at the point where the visit becomes unsafe
An officer may reach the property and find that access conditions have changed. A contractor may have closed part of the building, a common stair may be unlit, or a new sign may restrict access to part of the premises. Ask the designated site contact to confirm the restriction and any authorised alternative. If the answer is unclear, suspend that part of the visit and record the reason.
Before the first inspection, agree what the officer can do alone, how they check in and out, and who monitors that contact. Include what to do if the agreed check-in fails or the officer cannot confirm a safe way out. The HSE guidance on training, supervision and monitoring for lone workers explains why employers should set limits on lone work and test their contact and emergency procedures.
Use a status that reflects what was checked
Make the distinction clear in the first line of the report. The property manager should be able to see the status without reading the full log or interpreting a set of photographs.
- Completed: The agreed inspection scope was covered. Record any defects separately.
- Partial: Some agreed checks were carried out. List what was checked, what was missed and why.
- Missed: None of the agreed checks was carried out. If the officer attended, record the attendance and explain what prevented the inspection.
For example, an officer may complete the exterior checks from safe positions, then find that a contractor has restricted access to the interior. The report can say, “Partial visit. External checks completed. Internal checks deferred because contractor access restrictions were in place.” Any photographs should be labelled with what they actually show. Keep detailed findings and images within the agreed private reporting channel.
Give the property manager a decision to make
Send the exception to the named contact while there is still time to act. Include the visit date and time, the outstanding checks, the reason, any immediate action and the follow-up deadline. Agree an escalation contact for times when the primary contact is unavailable. A message sent to a shared inbox is easy to miss, so ask for acknowledgement when a decision is time-sensitive.
The property manager can then arrange access, ask the relevant site lead to clarify a restriction, or commission a competent person to assess a hazard. The security team should know which action it owns and what it needs from others before a return visit can go ahead. Where there is an immediate danger, follow the site’s emergency procedure.
Check the written inspection requirement before counting the visit
Compare the completed work with the agreed inspection schedule and any written insurance conditions. Some requirements specify both internal and external checks, the interval between visits and the records to retain. The policyholder or managing agent should check the actual wording and speak to the broker or insurer if the required checks may be missed. Ask whether any proposed alternative is acceptable and keep the written response with the site records. RICS guidance on property management and insurance explains how vacancy can change the conditions that apply to a property.
Keep attendance and completion as separate facts. If a perimeter check was all that could be done, record that visit at its actual time and arrange the outstanding checks as soon as they can be carried out safely. A later inspection should have its own date and record, linked back to the original partial or missed visit.
Close the inspection exception with evidence
Before sending someone back, confirm what has changed and who has authorised access. Give the returning officer the outstanding checklist, the relevant restrictions and the check-in arrangements. At handover, state what was subsequently inspected and identify any items still open. If the return visit uncovers a defect, give that defect its own action owner and follow-up. Use the vacant property defect follow-up guide to decide when that separate action can be closed.
If you are setting up checks for an empty commercial building, see our guide to agreeing inspection scope and vacant property security service. You can request a security quotation with the property type, postcode and inspection scope. Share any sensitive access information through the agreed private channel once arrangements are in place.